Geology and Technology

Great Divide Project

  • 95,000 net operated acres in main fairway
  • Acquired core holdings in January 2004
  • Location, Location, Location

    • Highway, infrastructure, south of Fort McMurray
  • Compressed timeline

    • March 2004 - Started field evaluation and delineation
    • August 2005 - Pod One application to EUB
    • July 2006 - Pod One EUB approval
    • October 2006 – First pile driven at plant
    • September 2007 – First steam
    • October 2007 – First bitumen sales
    • December 2007 – Start conversion to full time production

 

Pod One Plant


Built on time, pre-heat circulation phase concluding, full-time production underway

 

  • 15 well pairs drilled and completed
  • Encountered excellent reservoir
  • Less than 1m off basement
  • Steaming the wells
  • Conversion to production

 

Pod One Production Underway