Geology and Technology
Great Divide Project
- 95,000 net operated acres in main fairway
- Acquired core holdings in January 2004
- Location, Location, Location
- Highway, infrastructure, south of Fort McMurray
- Compressed timeline
- March 2004 - Started field evaluation and delineation
- August 2005 - Pod One application to EUB
- July 2006 - Pod One EUB approval
- October 2006 – First pile driven at plant
- September 2007 – First steam
- October 2007 – First bitumen sales
- December 2007 – Start conversion to full time production
Pod One Plant

Built on time, pre-heat circulation phase concluding, full-time production underway

- 15 well pairs drilled and completed
- Encountered excellent reservoir
- Less than 1m off basement
- Steaming the wells
- Conversion to production
Pod One Production Underway